Aligning the supply chain with business strategy

Review questions

Integrated summary: Aligning the supply chain with business strategy

Supply-chain alignment begins with the customer's actual choice: speed, specification flexibility or cost, alongside the quality needed merely to qualify. Choose the forecast-to-order boundary against feasible lead time and inventory exposure, then test process and layout against volume and variety. Faster delivery cannot be achieved by moving defects to a supplier or relying on nominal capacity. In make-or-buy, compare avoidable cost, qualification, drawing rights and bottleneck opportunity cost: making for 90,000 versus first-year buying for 94,800 differs from the 12,500-unit steady-state break-even. Resilience requires common-failure analysis: 200 units at 50 per day cover four days, leaving a 100-unit gap before an alternate clearing at day-six end. Sustainability claims need bounded measures and real data. Competitor evidence distinguishes a published offer from an executable improvement: removing one approval day from an eight-day flow supports testing seven days, not promising six without another verified change.

Review questions

Test your understanding with these questions. Marking and saved results are available with a free account.

  1. Question 1A standard finished product is stocked, the customer promise is two days, and shipping takes one. Which response meets the promise on the stated facts?
  2. Question 2Common parts are stocked, assembly takes two days, shipping one, and the Custom promise is four days. What are the path and slack before capacity waiting?
  3. Question 3The original workshop makes 60 A and 20 B units; each needs five test minutes and testing has a 480-minute shift. What is the test load?
  4. Question 4A dedicated A line can make 70 A after setup; demand is 60 A and 20 B. The line lacks the coating station B requires. How should its spare capacity be read?
  5. Question 5In a 120-order cohort, 101 orders jointly met the time, completeness, documentation and condition requirements. Which is the perfect-order rate?
  6. Question 6Among 19 nonperfect orders, nine have a recorded component delay, eight a documentation fault, and three have both. How many have at least one of the two recorded causes?
  7. Question 7At 12,000 units, make costs five each +30,000; buy costs 7.4 each +6,000 first year. Which is lower?
  8. Question 8What steady-state annual break-even volume solves 5Q+30,000=7.4Q?
  9. Question 9Consumption is 50/day and released stock 200. How many days does it cover?
  10. Question 10Alternate clears after end day six; stock covers four days at 50/day. What is the days-five-and-six gap?
  11. Question 11Stage lead times are 2+3+2+1 days. What share is approval?
  12. Question 12Of 40 documented lost deals, 24 cite lead time. What inference is supported?
  13. Question 13Opening stock is 80, output 120 and demand 100 in month one. What closing stock becomes month two’s opening?
  14. Question 14The three-month table ends month three at 50 against a closing-stock target of 60. Before seeing within-month order timing, what is the correct description?
  15. Question 15In the production exercise, level output closes at 40, 10 and 30; holding cost is two per unit at each month-end. What is carrying cost?
  16. Question 16Chase output is 60, 130 and 110, with a change cost of one per unit difference. What is within-horizon change cost?
  17. Question 17Opening stock is 30, baseline output 390 and campaign demand 450. What is the aggregate balance with no added options?
  18. Question 18Add 25 internal and 15 in-month supplier units at incremental rates of six and nine per unit. What are campaign closing stock and added supply cost?
  19. Question 19Week-one forecast is 90 and orders 60; orders consume same-week forecast down to zero. What are residual and planned demand?
  20. Question 20Week-two forecast is 110 and orders 125. Why is planned demand 125 rather than 235?
  21. Question 21At the end of week four, weeks three and four actuals are 90 and 110. What is the two-period moving-average forecast for week five?
  22. Question 22Naive forecast for week five is 110, moving average 100 and actual 120. Which comparison is sound?
  23. Question 23Actuals are 80,100,120,100 and forecasts 70,90,110,90. If error is actual minus forecast, what is CFE?
  24. Question 24Each of four periods has absolute error of ten units. What is MAD?
  25. Question 25Old baseline is 100 and new baseline 80; a promotion adds 50 new and diverts 30 from old. What is revised family demand?
  26. Question 26The new-model distributor opens with 20, receives 130 and sells 90 to consumers, with no loss or return. What is closing stock?
  27. Question 27Prior forecast is 100, latest actual 120 and smoothing α is 0.25. What is the next forecast?
  28. Question 28A new item has no sales history; service staff estimate 80–120 from installed base and an unverified failure rate. What is a disciplined start?
  29. Question 29C opens with 12, receives 45 in MPS and has 50 orders. What is week-end PAB?
  30. Question 30Testing load is 260 minutes; the nominal shift is 300 with 40 maintenance. What does RCCP show?
  31. Question 31Forty P are due week five, five usable P exist, and assembly lead time is one week. What are planned P receipt and release?
  32. Question 32Releasing 35 P in week four needs two A each. A stock is ten and scheduled receipt 20 in week four. What is A net need and release week with two-week lead time?
  33. Question 33Resource load is 320 minutes, shift 360, maintenance 40 and added outage 40. What is the gap?
  34. Question 34Eight C units can move to a qualified alternate taking five minutes each with 40 minutes free. What happens to original load?
  35. Question 35Common bases available are 15+30, with orders 20 red and 15 blue. What is base ATP before checking covers?
  36. Question 36Red needs 20 covers and has 18; blue needs 15 and has 20. What does FAS show before expediting?
  37. Question 37There are 80 old parts, 60 firm old-version needs before cutoff and book value four each. How should the remainder be described?
  38. Question 38New revision needs 45 parts, has five on hand, and supplier MOQ is 50. What are net need, order and stock after production?
  39. Question 39Production needs 150; 40 are available and supplier packs 30. What order size is feasible?
  40. Question 40Long supplier production takes 11 days, transit four and inspection two; units are needed on day 30. What is the latest cautious release?
  41. Question 41For 500 units, C and D each have landed cost 6,500; complete on-time rates are 95% and 90%. Which decision follows?
  42. Question 42What is C's landed cost per unit for 500 at 12 each plus 250 freight, 100 inspection and 150 expected defects?
  43. Question 43A job needs 180, has 30 on hand; 110 of a 150-unit receipt are released and 40 quarantined. What shortage remains?
  44. Question 44An alternate arrives late day four and needs a full inspection day; production starts day-five morning. What is its status?
  45. Question 45Need is 140, stock 30 and alternate MOQ 120. What remains after use if primary is cancelled?
  46. Question 46Alternate lead time is five days and need is day 18. What is latest release?
  47. Question 47Count 198 includes 30 customer-owned and 12 quarantined; 95 released company units are reserved. How many can serve a new order now?
  48. Question 48Company ERP shows 200; total count 198 includes 30 customer-owned. What is company book-versus-count variance?
  49. Question 49Daily mean 30, deviation eight, fixed lead four days and z=1.5. What is ROP with whole-unit safety?
  50. Question 50On hand is 80, confirmed open order 70 and backorders ten. What is inventory position?
  51. Question 51With D=10,000, S=40 and H=2, what is approximate EOQ?
  52. Question 52With MOQ 500 and packs of 250, which lot minimizes order-plus-carry cost among 500, 750 and 1,000?
  53. Question 53Book A 45/B 35; count A 33/B 47 with documented transfer 12 A-to-B. What entry is appropriate?
  54. Question 54After posting A-to-B transfer, C's book is 20 and count 19. What remains?
  55. Question 55Of 80 returns, 25 passed resale inspection and 20 await repair. How many are available now?
  56. Question 56What does 25/80=31.25% measure here?
  57. Question 57Jobs Y two hours due four, X four due five, Z three due eight. What total tardiness does EDD produce?
  58. Question 58EDD delays two jobs by two hours total; SPT delays one job by four hours. Which minimizes total tardy hours?
  59. Question 59A job is 240 units; 180 components are released and 60 held. What is safe initial release?
  60. Question 60At 60 units/day, held 60 are released end of day two. What is the earliest day for the fourth 60 in continuous sequence?
  61. Question 61Stable average WIP is 240 units and good throughput 80/day. What is implied flow time?
  62. Question 62Average WIP falls from 240 to 160 while throughput stays 80/day. What happens to implied flow time?
  63. Question 6380 of 200 were good by end day two, day three is down and day-four capacity 60. What is good total at end day four?
  64. Question 64Alternate makes 30 on day three, primary 60 day four, with 80 already good. What shortfall remains at day-four end?
  65. Question 65Branch B needs 70, has ten, targets ten ending and ships in multiples of 20. What dispatch is required?
  66. Question 66Goods are needed at start day 15 and transit plus release takes three days. What is latest dispatch?
  67. Question 67Released stock 100; A 60 full-priority, C 40 before B 50. What is today's allocation?
  68. Question 68100 of 150 demanded units are served today. What is immediate unit fill?
  69. Question 69Order B for 60 receives 50 by due date and ten tomorrow. Does order-level OTIF pass?
  70. Question 70A40 and B50 are confirmed by due date, total demand 200; D80 is disputed. What is confirmed on-time unit share now?
  71. Question 71Specification 98–102 and control limits 97–103; what does reading 102.5 mean?
  72. Question 72Reading 96.5 against specification 98–102 and control 97–103. What is initial judgment?
  73. Question 73Weld defect rate is 8% before and 5% after. What is relative reduction?
  74. Question 74Cracks are 4/800 before and 20/1,000 after. What numerical conclusion follows?
  75. Question 75Upfront 180,000, annual cash saving 90,000 and running cost 30,000. What is simple payback?
  76. Question 76Only half the expected benefit is realized: 45,000 yearly, running cost 30,000. What follows under a four-year screen?
  77. Question 77A demand 100, released 20 and quality-held 30. What is correct net requirement now?
  78. Question 78Systems agree for B and C but disagree for critical A due to quality status. What about automated launch?