Planning question and workforce baseline

Review questions

Subject 1 synthesis

Start with the service outcome rather than a vacancy count. Define the unique case, period and handling time, then ask which skill it needs and when. In the centre case, aggregate hours looked adequate while specialist review was short; removing duplicate transfer records changed the cover decision. A people count does not become productive hours without reconciling absence, work fraction and allocation across teams. The matrix adds a second check: job titles do not prove independent performance, and a supervised learner is not full ready capacity. The outputs are a decision card, a capacity bridge and a skill matrix, each with source, date and limit. Before using spare time, test whether it can move without causing another gap and whether it falls on demand days. A dated roster then tests whether monthly spare time conceals an early-week service shortage.

Review questions

Test your understanding with these questions. Marking and saved results are available with a free account.

  1. Question 1A team receives 600 unique cases a month, averaging 20 minutes each. What minimum additional input is needed to convert workload into full-time equivalents?
  2. Question 2In the team file Sarah offers 120 productive hours, Ali 60, Mary is away all month, Khalid's 120 are split equally across teams and Ali has a duplicate row. What confirmed capacity belongs to this team?
  3. Question 3At the service launch Layla is independent in capacity and quality but available half-time; Salem is full-time and independent in capacity. What is their maximum capacity-analysis supply before Layla is assigned to quality?
  4. Question 4A fictional centre needs 60 qualified review hours in week one but has 50, while the month shows 20 spare hours overall. What follows for week one?